EAST COAST ENERGY PVT LTD
Committed to Sustainable Development
PROJECT UPDATE

Project Land

Andhra Pradesh Industrial Infrastructure Corporation (APIIC) has transferred the title of land to ECEPL.

EPC Contract

The Boiler – Turbine - Generator (BTG) is being supplied by Dongfang Electric Company (DEC), Republic of China.

Fuel

  1. Domestic: Coal Linkage for 70% of the coal consumption for Phase – 1 (2x660 MW) has been allocated from Mahanadi Coal Fields Limited, Orissa. The Letter of Assurance (LOA) has been issued by MCL.
  2. Imported: ECEPL has signed Fuel Supply Agreement for supply of imported coal with Global Fuels Pte. Ltd. for 30% of the fuel required. Ministry of Coal, Govt. of India has stipulated that coastal based plants need to source 30% fuel from outside the country.

Environmental Clearance from Ministry of Environment and Forests has been received for 2640 MW (click for EC copy)

Environment Clearance from State Level Environment Impact Assessment Authority has been received for Township Phase – II (click for EC copy)

Company has received accreditation from TUV – SUD, Asia Pacific for implementing the OHSAS 18001: 2007 certification for the project (click for Certification)

Consent for Establishment obtained from APPCB.

No objection certificate (NOC) received from Ministry of Defense.

All mandatory clearances from statutory bodies have been obtained.

Long Term Power Purchase Agreement has been signed with PTC India Limited for off take of 300 MW of power.

Environmental and CRZ clearance received for the construction of intake facilities of drawl of sea water and discharge of waste water facilities including construction of jetty for the project (click for EC copy)

Long term Open Access has been applied for and the CTU (PGCIL) has commenced related system strengthening studies. PGCIL has included the project in southern region studies and revised load flow studies are being made.

ACTIVITIES AT PROJECT SITE

Infrastructural works

  • Site office, Storage Sheds, Fire Station Complex, Security Gate Complex and Dormitory are completed
  • Facilities like Weigh Bridge, Oil filling station, Nursing station, Nursery for Green belt development, construction water reservoir and power are operational at the site
  • Fire engine is positioned at site
  • Piling for canteen building completed and pile cap works in progress
  • Piling for Admin building in progress
  • Site grading works in progress
  • A total of 210 Cum/Hr batching plants with varying capacities is operational at project site

BoP & BTG Works

  • Engineering design for major structures is completed
  • Major order placement completed

BoP Works

  • Piling works for chimney and boiler completed
  • Piling works in progress for TG building and ESP
  • Pile caps in Boiler area and Chimney are in progress

BTG Works

    Ten shipments comprising boiler embedded parts, structural steel material of BTG, anchor bolts, valves etc., have been received from BTG contractor – Dongfang Electric Corporation, (DEC) Chengdu, Republic of China.

Residential Colony

  • Infrastructure works completed
  • Field Hostel is completed and occupied
  • Ten blocks of staff quarters completed, out of which four blocks are occupied
  • Remaining Quarters construction is in progress

Greenbelt and Nursery

    Work in Progress

Compliance to Environmental Clearance

  • Submitting regular compliance statements to MoEF & APPCB in accordance to Environmental Clearance issued. (Latest Report)
  • Construction within the project site is limited to an area of 1317 acres in compliance to MoEF/NEAA order.